United Blythe Joint Venture (UBJV) has planned to switch traffic to the next phase of construction for the above-referenced project starting next week according to the schedule below. Please note that these dates are subject to change based on weather conditions. Be prepared for lane closures and changing traffic patterns on I-77 and at the interchange with SC 160 as this work unfolds.
1. Sunday night 1/26 - I-77 SB Phase 2 Traffic Shift (moving traffic to the outside shoulder of I-77)
2. Monday night 1/27 - Traffic shift onto the New I-77 Northbound on-ramp
3. Tuesday night 1/28 - I-77 NB Phase 2 Traffic Shift (moving traffic to the outside shoulder of I-77)
4. Tuesday night 1/28 thru Friday night 1/31 - Installation of Median Temporary Concrete Barrier Wall on I-77